As part of the ongoing reconstruction of the Auezov Street bridge, concrete beams have been delivered from the city of Almaty. Currently, installation works are underway for five beams, each 24 meters in length.
Since there are two bridges on this section, a total of 22 beams will be installed. The remaining beams will be delivered gradually, with new deliveries arriving each day.
The total width of the bridge will be 24 meters, and the combined length of both bridges will reach 70 meters. The project will include four traffic lanes and sidewalks on both sides of the road, each three meters wide. All construction works are being carried out according to the approved schedule.