Road workers from the municipal enterprise BishkekAsphaltService continue efforts to improve the city’s infrastructure.
Currently, major repairs are being carried out on Levanevskogo Street, from Gagarin Street to Building No. 136A.
As of today, curb installation along the roadway has been completed, work on sidewalk curbs on the western side is ongoing, and the irrigation system is being installed. Simultaneously, preparations are underway for the sidewalk base.
As part of the major repairs, fences and structures that extended beyond the red line were dismantled. The clearance of municipal land has widened the street, allowing sidewalks on both sides of the road and the installation of the irrigation system.